Vide Letter No. GERC /Tech/2010/2066 dated 30 December, 2010 approved to recover following

charges from 1st January 2011 from the prospective LT consumers.

Schedule of Charges to be recovered :

 

New Connection / Extension / Reeducation / Shifting

 
  Load in kW  (aggregatee)

Amount Rs.

i Not exceeding 2 kW Rs. 3,500.00
ii Exceeding 2 kW but Not exceeding 6 kW Rs. 5,000.00
iii Exceeding 6 kW but Not exceeding 12 kW Rs. 8,500.00
iv Exceeding 12 kW but Not exceeding 20 kW Rs. 14,500.00
v Exceeding 20 kW but Not exceeding 40 kW Rs. 20,000.00
vi Exceeding 40 kW but Not exceeding 60 kW Rs. 30,000.00
vii Exceeding 60 kW but Not exceeding 80 kW Rs. 60,000.00
viii Exceeding 80 kW but Not exceeding 100 kW Rs. 90,000.00

All categories of prospective new consumers for Load Extension / Reduction / Shifting / PDC

reconnection etc. at the rates stated as above, except Agriculture Tatkal Category and LTP-V

category.     Effective from 1st January,2011.                         No past cases are to be reopened.